    Summer improvement projects underway at Cal Poly 

    University Union – dining complex building 19 & 19A rendering. 

    Developments may cause temporary inconveniences for employees, students, and campus visitors

    – Summer at Cal Poly is busy with nearly a dozen major capital projects in support of the university’s master plan. The projects include building the John Madden Football Center, reconfiguring the administration building parking lot, renovating the interior of the university union, expanding the technology park, and beginning the Kennedy Library transformation.

    While these developments are intended to enhance the quality of university life, they may create temporary inconveniences for employees, students, and campus visitors. To assist in navigating these changes, a comprehensive list of the projects that might impact traffic and parking is listed below.

    John Madden Football Center
    Work begins: Summer
    Parking impacts: C3 and C4 lots closing June 19
    Road impacts: College Avenue, Sept. 21–Nov. 1; Dec. 18–Feb 14, 2024
    South Perimeter Road, June 19–Sept. 15

    A1 parking lot reconfiguration
    Work begins: June
    Parking impacts: A1 parking lot closed June 26–late fall 2023

    University Union renovations
    Work begins: June
    Building impacts: The entire first floor of the building will be closed from June 19 to Sept. 14, including the Craft Center, Multi-Cultural Center, Starbucks, Market University Union, Mustang Station, Red Radish, and Mustang Lanes. Starbucks will maintain service via a mobile unit located in the University Union Plaza during the closure.
    Parking impacts: none
    Road impacts: Poly View Road is expected to be closed to vehicle traffic, June 1-July 7. There will be no pedestrian impacts.

    Sports Complex Road Repairs
    Work begins: June
    Parking impacts: none
    Road impacts: Flagging traffic to the Swine Unit

    Agricultural Sciences Building (No. 11) Roof Replacement
    Work begins: June
    Parking impacts: none
    Road impacts: Intermittent flagging on University Drive adjacent to the building

    Robert E. Kennedy Library Transformation
    Work begins: Aug. 25, 2023
    Parking impacts: Closure of the back end of C7 parking spaces, which will serve as a temporary study space throughout the project’s duration.

    Several parking lot projects will also be taking place throughout the summer involving resealing, re-asphalting, and restriping. The work will be completed in phases, with one lot impacted at a time. Specific dates for each lot closure have not yet been determined. Affected lots include G2, H4a, H4d, H4e, C2d, and C2c. For more information on parking lot closures, visit the Transportation and Parking Services webpage.

    For a complete list of current capital projects visit the project news page.

     

    Share To Social Media
    Follow this discussion
    Notify of
    0 Comments
    Oldest
    Newest Most Voted
    Inline Feedbacks
    View all comments
    About the author: News Staff

    The news staff of the Paso Robles Daily News wrote or edited this story from local contributors and press releases. The news staff can be reached at info@pasoroblesdailynews.com.

    Follow this discussion
    Notify of
    0 Comments
    Oldest
    Newest Most Voted
    Inline Feedbacks
    View all comments
    Subscribe button for Paso Robles Daily News
    0
    Would love your thoughts, please comment.x
    ()
    x