City approves 45 blocks of street improvement 

–At Tuesday night’s Paso Robles City Council meeting, the council unanimously approved awarding contracts for hotspot street repairs and slurry seal repairs for a collective 45 blocks of city streets.

In June 2015, council adopted an expenditure plan based on a projected revenue of $1,429,000 from Gas Tax and Transit Funds.City council meeting Paso Robles Oct 20

The adopted expenditure plan is as follows:

• Airport road maintenance: $600,000 (Propeller to Tower)
• Hotspot repairs: (various locations) $200,000
• Slurry seal: (of several streets) $629,000

Staff advertised for bids for both projects, and at the bid opening on Oct. 1, bids were received as follows:

Hotspot street repairs:
• Souza Construction: $235,000
• Viborg Sand & Gravel: $306,838.50
• John Madonna Construction: $462,821

Slurry Seal Repairs (base bids):
• Souza Construction: $728,212
• Intermountain Slurry Seal: $798,787.44

There are 9 locations for the hotspot repairs. The following streets are on the project list for maintenance:

  • Navajo Court
  • Navajo Avenue – South River to north of Cheyenne
  • Mohawk Court
  • Rainbow Court
  • Cheyenne Drive (loop road)
  • Pawnee Court
  • Shoshone Drive
  • Navajo cul-de-sac
  • Rose Lane – Navajo to Bolen
  • Cherokee Court
  • Apache Court
  • Crazy Horse Drive – Navajo to Nickerson
  • Chumash Court
  • Sacagawea Court
  • Pocahontas Court
  • Red Cloud Road – west of Rose Lane to Nickerson

Staff needs assistance from Pavement Engineering Inc. to provide construction inspection, testing, and monitoring the contractors’ progress (i.e. prepare daily reports, measure actual work done for payment, review material compliance reports, insure contractors meet specifications, etc). Their fee for services for both projects is $95,000.

Staff reviewed the low bids submitted by Souza Construction in the amount of $235,000 for hotspot repairs and in the amount of $728,212.80 for slurry seal repairs, and found both to be responsive and responsible bids.

The total amount approved to be awarded is $1,058,212.80, with a 10-percent contingency of $105,800.20 for a total of $1,164,013.